Reviewed September 7, 2026.
DOB’s current published civil penalties for violating a stop-work order are $6,000 for the first offense and $12,000 for subsequent offenses. These replace the older amounts previously stated here. Other violations and penalties may also apply. See DOB’s stop-work order guidance.
A full order stops work except authorized remedial work needed to make the site safe. A partial order restricts the work or area identified. Read the actual order and coordinate any permitted corrective work with the issuing unit; do not decide unilaterally that ordinary construction can continue.
Correction does not automatically rescind the order
Address the cited conditions, provide required correction documents, request reinspection, pay applicable civil penalties and obtain rescission from the issuing unit. For work stopped because no permit existed, obtaining a permit alone does not authorize resumption while the order remains in effect.
Owners and contractors should also document the effect on schedule and costs, give required contract notices and coordinate with design professionals. Handle OATH summonses, correction certification and removal of the stop-work order as related but distinct tasks.
Kushnick Pallaci PLLC assists clients throughout New York with DOB enforcement and construction disputes. Contact 631-752-7100 or vtp@kushnicklaw.com.
Attorney Advertising. General information, not legal advice.