Decided November 16, 2015 at Sup. Ct., New York County
This case presented the classic issue of whether a subcontractor has a valid cause of action for unjust enrichment against the
owner of property, where the governing contract was between the subcontractor
and the general contractor.
Here, Plaintiff, the owner of the property
at issue, hired and entered into a contract with a general contractor, A.J.S.
Project Management Inc. (“AJS”). AJS
then hired various subcontractors, with whom Plaintiff had no contractual
relationship with, to assist on the construction on the property. Certain subcontractors filed mechanic’s liens
on the property, based off of money owed to them by AJS. Plaintiff brought suit seeking a declaratory
judgment that Plaintiff is not liable to the subcontractors for any money due
and owing between them and AJS. One of
the subcontractors, Hudson Concrete Publishing Inc. (“Hudson”) alleged certain
counterclaims against Plaintiff, including a claim for unjust enrichment,
wherein Plaintiff moved to dismiss Hudson’s counterclaims for failure to state
a cause of action. This decision addresses
the Plaintiff’s motion to dismiss.
The Court explained that, as a general
rule, a quasi-contractual claim, such as unjust enrichment, is ordinarily
precluded where there is the existence of a valid and enforceable contract
which governs the events arising out of the same subject matter. This general rule is applicable to claims
brought against non-signatories, precluding quasi-contract claims being brought
against third party non-signatories to a contract that covers the same subject
matter of the claim.
Under a quasi-contract claim, “if services
were performed at the behest of someone other than the Defendant, the Plaintiff
must look to that person for recovery.”
Thus, it is not enough that the Plaintiff received a benefit from
Hudson. The Court ruled that where an
express contract exists between the general contractor and the subcontractor,
the mere owner of the property where the work is being done may not be held
directly liable to the subcontractor under a quasi-contract theory “unless he
assented to such an obligation.” Thus,
the sole remedy of a subcontractor lies against the general contractor with
whom the contract was entered into with.
Hudson admitted to being hired by AJS, the
general contractor, and failed to assert allegations linking Plaintiff to the
services it alleges to have performed on Plaintiff’s property. As Hudson sought payment for services
performed under its contract with AJG, the claim is governed by the terms under
that contract, thus the quasi-contract claim against the Plaintiff must fail.
No comments:
Post a Comment