The
parties entered into a subcontract for plaintiff to perform certain remediation
work upon the discovery of mold during construction. An alternative dispute resolution (“ADR”)
provision was included in the subcontract, which provided that the contractor’s
representative could decide all questions arising from the subcontract and the
decision shall be binding and conclusive.
A law suit could be commenced if the subcontractor disagreed with the
representative’s finding, but the court shall be limited to determining whether
the representative acted arbitrarily, capriciously, or grossly erroneous to
evidence bad faith.
This
suit arose out of the representative’s rejection of plaintiff’s claim that it
was due certain payments on the subcontract.
The representative determined that plaintiff was 30% responsible for the
outbreak of mold and therefore the unpaid balance owed to plaintiff was to be
offset by 30% of the total damages that defendant incurred to remediate the
mold. The lower court found questions of
fact remained and therefore denied both parties’ motions for summary
judgment.
On appeal, defendant claimed that
pursuant to the ADR provision, only a limited review was to occur and that by
the court finding questions of fact, the court was required to find that the
determination had a factual basis and therefore was not arbitrary and
capricious. The Appellate Court
disagreed with this conclusion.
The Court found that the provision
at issue called for broader judicial review, similar to that under CPLR 78, not
the stricter standards of arbitration review under CPLR 75. The Court ruled that since the contract
embraced a claim of bad faith, it would be inappropriate to accord the
representative’s determination the same deference accorded to a discretionary
determination made by an administrative agency.
Decided 1/22/15 at App. Div. 3d Dept.
No comments:
Post a Comment