The
Appellate Court affirmed the holding of the lower court, finding in favor of
Koko Contracting, Inc. U.W. Marx, Inc. was
the general contractor on a construction project and entered into a subcontract
with Koko for roofing work. Marx failed
to pay Koko for 3 consecutive months, wherein Koko, on October 31, 2007, ceased
performance on the roof. Marx gave Koko
3 days’ notice to cure its alleged default (failing to provide workers) wherein,
on November 6, 2007, Koko provided Marx with the 7 days’ notice of its
suspension of work based on nonpayment as called for in a section of the
subcontract.
Marx
argued that Koko should be precluded from recovery due to its non-compliance
with the provision in its subcontract (a standard provision clause drafted by
the American Institute of Architects) which required 7 days’ notice to be given
prior to ceasing performance of the contract.
The Court held that Marx’s material breach, i.e. non-payment, was an
“uncured failure of performance,” and therefore Koko was relieved from its
remaining obligations under the contract.
Essentially, Marx’s material breach excused Koko from any of its own
obligations set forth by the contract.
Furthermore, the Court explained that such a provision is not
meaningless, as it is there to protect the subcontractor and to compensate it
in the event it has to stop work for lack of payment and then remobilize.
Decided 1/21/15 at App. Div.
2d Dept.
No comments:
Post a Comment